As you can see, there are three courses of cement blocks on top of the concrete pads that we poured.
Martin needed to back fill inside of the foundation to have the ground nearly level to the top of the cement blocks. We will be pouring a slab once it is backfilled and the weather is warm enough
The picture below has the barn foundation back filled. It took a couple of days with a backhoe and a lot of back-breaking work to spread the sand, level it, tamp and roll it so it is well packed.
Above is the sandpile before the barn foundation was backfilled.
Below is what is left.
No comments:
Post a Comment