Sunday, August 2, 2015

forward progress on the septic system

 Once the leach field was dug out, we ordered a couple of truck loads of gravel. The gravel needed to be spread out evenly throughout the leach field and then leveled.






 Once Martin got the gravel spread and leveled, he rented a compactor to firm it up.
Then we put the drainage pipes together. Martin needed to dig out trenches in the gravel where the drainage pipes needed to be placed.
 Lastly, the distribution box was put in place.
Now we just need to have it inspected again before we can fill the hole back in and have a yard again.
 In the meantime, Martin got started on digging out the hole for the septic tank.